What is the construction process of steel sheet piles

1. Firstly, the steel sheet piles should be processed, and the surface defects should be treated well, and the length, width, lock shape and other components should be inspected. If there are affected weldments, they need to be disposed of in advance. If there is serious corrosion, the actual thickness needs to be measured and reduced.

2. Install the guide frame. The guide frame is generally composed of guide beams and purlin piles. It can be divided into single-sided and double-sided in terms of square meters, and can be divided into single and double-layer in terms of height. In addition, the distance between purlin piles is 2.5 to 3.5m, and the distance between purlin piles on both sides will be about 8 to 15mm larger than that of plank bricks.

3. Pile caps can be set in pile hammers and steel sheet piles, so that they can be evenly distributed, so as to ensure that the pile tops are not damaged.

4. Use a crane to move the steel sheet piles to the designated place for pile insertion. Pay attention to the tightness of the locks, and each time a piece is inserted, the pile cap must be put on and tapped gently to ensure that there will be no problems.



Precautions for steel sheet pile construction

1. The personnel who carry out the construction of steel sheet piles need to have a certain understanding of the construction plan and have rich experience, so that they can make reasonable adjustments in case of emergencies. In addition, the construction site needs to be dealt with to avoid the existing obstacles from having a greater impact on the construction.

2. In the construction area, it is necessary to make obvious signs and make necessary construction lighting equipment, so as to ensure normal construction. Moreover, the rubbish and waste materials generated during construction should be disposed of in time.

3. For the construction tools and mechanical equipment on site, the inspection work must be done in advance, so that the existing safety hazards can be dealt with.

Know more about this product price, catalogue, mill test certificate,  please inquiry to: [email protected]

Contact

We use cookies to offer a better browsing experience, analyze site traffic, and personalize content. By using this site, you agree to our use of cookies.

Accept
Decline